Add lag or lead time to task links
From the course: Microsoft Project 2021 and Project Online Desktop Essential Training
Add lag or lead time to task links
- [Instructor] Sometimes there's a delay or overlap between linked tasks. Project links can handle these delays and overlaps. Before we dig into how that works, I want to show more of the time scale. So I'm going to point at the vertical divider between the table and the time scale. And when I see the double headed arrow, I can drag to the left and now I have more timescale displayed. Now we're going to go down in the list in this project and find task 32, obtain permits. Let's say that there's a three week delay to get the permit to proceed. So demolish walls has to wait until you've got the permit. We're going to create a link between task 32, obtain permits, and task 34, demolish walls and add a lag to it. So what I'm going to do is I'm going to create this link in the task form. So what I want to is the successor task, demolish walls. Then I'm going to go to the predecessor cell in the task form, click the down arrow, and I want to scroll up a little bit and select obtain permits.…
Practice while you learn with exercise files
Download the files the instructor uses to teach the course. Follow along and learn by watching, listening and practicing.